Large Scale Banking Data Migration & Validation

Where
F1Soft International
Role
Project Manager
Stack
SQL, Oracle DB

Problem

Migrating over 100,000 legacy customer records to a new system carried high risk of data loss, duplication, or service disruption during cutover.

How It Was Built

Migration ran in controlled phases rather than as a single cutover event: a validation pass checked source data integrity before migration, a staged cutover moved data in verifiable batches, and a post migration verification pass reconciled record counts and checksums against the source system before the legacy system was retired. Rollback readiness was maintained at every stage, so any phase could be reversed without touching data that had already been verified.

Key Technical Details

  • Pre migration data integrity validation
  • Staged, verifiable cutover execution
  • Post migration verification and reconciliation
  • Rollback readiness maintained at every phase

Results

  • Migrated 100,000+ customer records with zero data loss
  • Zero rollback required
  • Minimal service disruption during cutover